Builders Risk Insurance: Covering a Project Under Construction
Builders risk is property insurance for a building while it is being built or renovated. It protects the project itself: the structure, the materials that will become part of it, and often the temporary items needed to build it. It is not the liability insurance a contractor carries all year, and it is not the same as coverage for a contractor's own tools.
What builders risk covers
The NAIC glossary describes builder's risk as coverage against loss to buildings in the course of construction. It adds that the coverage is typically written on a reporting or completed-value form, and that it can include machinery and equipment used in construction and materials incidental to the construction.
It is sometimes called "all risk" or "course of construction" insurance. The University of California describes it as protecting the owner, contractors and subcontractors of all tiers against direct physical loss or damage to the project from a covered peril, such as fire or theft.
Sample contract requirements show what owners ask for. One Ohio university consortium's model language calls for coverage of work in progress, including falsework, temporary buildings and structures, and materials used in construction, whether stored on or off the site or in transit. These are examples of what owners demanded, not a standard every policy meets.
Who buys it
There is no single rule. Dartmouth says the owner or the general contractor typically buys it, with coverage extending to the owner, the general contractor, some or all subcontractors, and material suppliers. The University of California buys its own builder's risk program and requires it for its projects at or above a stated construction cost, while the University of Colorado's language, in contrast, has the contractor buy it unless the owner instructs otherwise.
Lenders can also set the requirement. Fannie Mae's multifamily guide, for example, says that where property insurance is excluded during construction, renovation or restoration, builder's risk must be in place for the whole construction period, from the construction start date to the completion date. Other lenders differ, so read your loan documents.
Check the contract so that one party clearly insures the project, and ask who is named as insured and loss payee.
When coverage starts and ends
The start and end are contract and policy terms. Under the University of California program, coverage begins on the notice to proceed for the construction phase and must be requested before work begins at the site. It ends at final completion as stated in the notice of completion, not at occupancy. It says verbal or email notice of an extension does not extend coverage.
Other documents choose different triggers. Colorado's language keeps the policy in force until final payment or until no one other than the owner has an insurable interest. The Ohio consortium's model language requires the policy to permit partial occupancy by the owner and to stay in effect until punch list items are finished.
If anyone will occupy part of the building before it is finished, ask whether the policy allows it. The sources here do not say what happens if it does not, so get the answer in writing.
Completed value, reporting and project cost
The NAIC says builders risk is typically written on a reporting or completed-value form. The sources here do not compare the two in detail, so ask what value sets the limit and what you must report.
Owner contracts commonly set the limit at the full completed value. The Ohio consortium and Colorado examples each call for 100 percent of completed value on a replacement cost basis. The University of California program bases its premium on construction cost and the number of construction days, asks that cost increases of 5 percent or more be reported, and requires notice if the project goes over the policy limit.
The University of California counts materials, equipment and fees tied to construction, but leaves out pre-construction design phases and demolition or abatement costs. Your policy may differ.
Soft costs and delay in completion
Soft costs are indirect costs of a delay after a covered loss, not the repair itself. The University of California's program lists delay in completion among its excluded items unless it is specifically purchased as an option. The Ohio consortium's model language, by contrast, asks owners' contractors to include a soft cost endorsement covering reasonable extra costs of the architect or engineer and of acceleration, plus a provision for extra expediting costs.
Do not assume soft costs or delay are included. Ask how the policy defines them.
Materials off-site and in transit
Materials are often bought and stored before they reach the site. The University of California's policy includes sublimits for materials in transit and offsite storage. A sublimit is a cap lower than the project limit. The Ohio and Colorado samples ask for coverage of materials in transit or stored off-site, and
Common exclusions and limits
Exclusions differ by policy, and some can be bought back. The University of California's FAQ lists excluded perils as earthquake, land movement, flood, terrorism and delay in completion, unless specifically procured as an option. Yet the Ohio and Colorado samples ask for earthquake and flood to be included, so coverage is often negotiated.
Dartmouth highlights one exclusion that surprises owners: interior damage to a building under construction from rain, sleet or snow when the roof, walls and windows are not yet complete.
Theft rules are not uniform either. Dartmouth lists theft among covered events, and the Colorado sample requires it, but your policy may restrict it. The sources used here do not address exclusions for faulty workmanship or wear and tear, so ask your agent exactly how the policy treats defective work and resulting damage.
Deductibles matter too. In the University of California program the contractor is responsible for the per-occurrence deductible, as the university's contracts provide. Sample contracts cap acceptable deductibles at $25,000 (Ohio) and $50,000 (Colorado). These are institution-specific figures, not market benchmarks.
New construction and renovation
Triple-I describes the coverage as applying to both new construction and renovation. The Colorado sample requires it for new buildings or additions, and for materials and equipment to be installed in existing structures. The Ohio sample says a firm that only installs materials and equipment, and does no new building construction, may need a builder's risk, builder's risk renovation or installation floater policy instead.
The University of California says it is not needed while only demolition is occurring. On a renovation, ask how the existing building is insured; the sources here do not say.
How it differs from other coverages
Builders risk is first-party property coverage. It pays for damage to the project itself. Other coverages respond to different problems:
- General liability: the NAIC defines comprehensive general liability as coverage of all business liabilities unless specifically excluded in the policy.
- Completed operations: the NAIC describes it as liability coverage for contractors for bodily injury or property damage from defective work completed or abandoned away from the insured's premises.
- Inland marine and equipment floaters: Triple-I says inland marine covers property in transit, and lists construction and contracting equipment among its items. Its small-business guide explains that machinery and equipment moving from job to job is insured through floaters, and that an installer's floater covers equipment in transit, installation and testing at a customer's premises.
| Coverage | What it protects | Type |
|---|---|---|
| Builders risk | The building, materials and often temporary structures during construction or renovation | Property (first party) |
| General liability | Claims by others for injury or property damage | Liability (third party) |
| Completed operations | Claims from defective finished work | Liability (third party) |
| Inland marine / equipment floater | Movable equipment, materials in transit | Property (movable) |
Ask whether contractors' tools are in the project policy or a separate floater.
Wrap-up programs
On some large projects the owner buys insurance for everyone. The Federal Highway Administration describes an owner controlled insurance program, also called wrap-up insurance, as coverage the owner buys on behalf of the builder instead of each party buying its own. Its listed lines include workers compensation, general liability, excess, pollution, professional liability and builders risk. Contractors still insure their own off-site work. Your contract will say what a wrap-up includes.
If there is a loss
Follow the policy's notice rules. In the University of California program, losses must be reported within 24 hours. That is one owner's rule. Ask early how and when to report, and who receives payment.
Questions to ask an agent
- What limit and valuation apply, and how are changes in cost or scope reported?
- When does coverage start, and when does it end: occupancy, substantial completion, final payment or a notice of completion?
- Does the policy permit partial occupancy, and what must I do before the owner or tenants move in?
- Are soft costs and delay in completion included, and how are they defined?
- What sublimits apply to materials in transit, off-site storage, water damage, theft and temporary structures?
- Are flood and earthquake covered, excluded or available as an option?
- How does the policy treat defective work and the damage that results?
- Are contractors' tools covered here or by a separate equipment policy?
- Who is named as an insured and who is the loss payee, as the contract and lender require?
- What are the deductibles and who pays them?
Find an agency
Browse builders risk agencies in our directory, then confirm the agency is licensed in your state using our guide to checking an agency's license.
Frequently asked questions
Is builders risk the same as general liability?
No. Builders risk is property insurance that pays for damage to the project being built. The NAIC describes comprehensive general liability as coverage for business liabilities, which means claims by other people. A contractor usually needs both, and the contract may require specific limits for each.
Who is responsible for buying builders risk?
It depends on the contract and sometimes the lender. Dartmouth says the owner or general contractor typically buys it. Some owners buy it themselves, while others require the contractor to. Read the construction contract and loan documents, and make sure one party clearly carries it.
When does builders risk coverage end?
It depends on the policy and contract. The University of California ends coverage at final completion stated in a notice of completion, while other documents use substantial completion or final payment. Occupancy can matter, so ask whether partial occupancy is allowed before anyone moves in.
Does builders risk cover delays or lost income?
Not necessarily. The University of California program excludes delay in completion unless it is bought as an option, and one Ohio model contract asks for a soft cost endorsement. Ask how your policy defines soft costs, and what limit and waiting period apply.
Does it cover materials that are not on the site yet?
Often through sublimits, but not always. The University of California's policy has sublimits for materials in transit and offsite storage, and sample contracts from Ohio and Colorado ask for such coverage. Confirm the limits and any conditions, such as identifying the stored materials.
Does it cover a contractor's tools and equipment?
Sometimes. The NAIC says builders risk can include machinery and equipment used in construction. Triple-I explains that equipment that moves from job to job is usually insured through floaters. Ask whether your tools are in the project policy or need their own.
Sources
- NAIC: Glossary of insurance terms
- Triple-I: Understanding inland marine insurance
- Triple-I: Insurance for artisan contractors
- University of California Office of the President: Builder's Risk Insurance FAQ
- University of California Facilities Manual: Beneficial Occupancy and Substantial Completion
- Dartmouth College Risk Management: Builders' Risk
- IUC Risk Management and Insurance Consortium (Ohio): Contractual insurance guidelines
- University of Colorado: Construction contract insurance requirements
- Federal Highway Administration: Owner Controlled Insurance Programs (Wrap-Up Insurance)
- Fannie Mae Multifamily Guide: Builder's Risk Insurance